What is in a construction management plan?#
Per the TfL and CLOCS definition, a CMP details the procedures, sequencing and methodology for a construction project, aimed at demonstrating how the impact of construction can be minimised in relation to both on-site activity and the transport arrangements for vehicles servicing the site. In practice that means programme and phasing, site set-up, how the work will be carried out, and how vehicles serving the site will be managed.
How to write a construction management plan?#
Start from the condition wording and answer it point by point, because the condition is what has to be discharged. Then build the content out: programme and phasing, site set-up and hoarding, working hours, how the work will be done, vehicle routing and access, deliveries and waste, and how neighbours will be kept informed. Name who is responsible for each commitment. A plan that describes activity without naming responsibility is the most common reason for a request for further information.
When is a construction traffic management plan required?#
When the planning authority conditions one. Authorities attach the requirement where construction traffic could affect the public highway, which typically means constrained access, a nearby school, a bus route, a controlled parking zone, or simply the volume of deliveries the build will generate. It is the condition, not the scheme size, that creates the obligation.
What does a CTMP need to contain?#
Drawing on what authorities typically ask for: the construction programme and phasing, vehicle types and sizes, expected movements by phase including the peak, approved routes to and from the site, site access and egress points, loading and unloading arrangements, any parking suspensions or road closures needed, wheel washing and highway cleanliness, pedestrian and cyclist protection, and how the plan will be monitored. Always check your authority's own pro-forma, because several publish one and expect it used.
What is the main purpose of the construction phase plan?#
Planning health and safety for the construction phase specifically, as distinct from designing the finished building safely, which is the designer's duty, and from the health and safety file, which concerns the completed structure. Each CDM document covers a different period.