What is the difference between a CTMP, a CMP, a CLP, a CEMP and a construction phase plan?#
They are five different documents and only three of them are planning documents. A Construction Traffic Management Plan and a Construction Logistics Plan both deal with construction vehicles, routing and highway impact, and are required by the local planning authority. A Construction Management Plan is broader and, per the TfL and CLOCS guidance, details the procedures, sequencing and methodology for a project covering both on-site activity and the transport arrangements for vehicles servicing the site. A Construction and Environmental Management Plan covers how the project will avoid, minimise or mitigate effects on the environment. A construction phase plan is not a planning document at all: it is required by regulation 12 of the Construction (Design and Management) Regulations 2015 and deals with health and safety.
Which of these documents does my planning condition mean?#
Read the condition wording, not the acronym. If it asks for vehicle routing, access, wheel washing, delivery scheduling or construction vehicle numbers, it means traffic and logistics content whatever it is titled. If it asks about noise, dust, working hours and ecology, it means environmental content. If it mentions health and safety arrangements or site rules, that is a construction phase plan and it is not normally secured by planning condition, because it is already a statutory duty.
Do you need a construction phase plan for maintenance work?#
It depends on whether the work is construction work within the meaning of the regulations, which is a legal question about the nature of the work rather than what it is called. Routine servicing generally is not; refurbishment, repair and alteration generally are. This is a point to confirm with a competent health and safety adviser for your specific activity.